Case History

Cormac projects

Project: Mormoyle - Barrangaroo Tower 1,2 & 3 Assorted flues to 7t - 85/15 and painting -50 year service

Project: PKCT - 110 Spine beams - 2016


Project: Newcastle Port Corp - 500m of seawall. UHPWJ paint removal and recoating - 2015


Project: SHELL Prelude –  TSA application 16 Well heads & 18 fatigue joints - 2014

Project: Lychee Project Malaysia
Client: KNM Fabrications/Foster Wheeler -Gebang Malaysia 
Scope: TSA of three 1300kg 21m L x 4.5mt dia tanks
Installation date: Feb 2014

Project: SKARV Turret, Keppel Fels Shipyard/ASH Marine - Singapore -BP built by SBM 2010

Project: GUMUSUT FFPSO
Client: MMHE Shipyard - Malaysia
Owner: SSPC SHELL/Petronas
Scope: TSA of Cassion pipes internal & external & sealer
Installation date: Aug 2011 to Jan 2012

Project: Flare tower - TSA & HT aluminium silicone ealer application
Client: Sembawang Shipyard    JV - ASH Marine
Owner: Maersk Ole
Scope: TSA of 4500 m2 entire flare tower
Installation date: October 2010 – Dec 2010

Project: Haf Dan- TSA & HT aluminium silicone ealer application
Client: Sembawang Shipyard    JV - ASH Marine
Owner:Maersk Ole
Scope: TSA of 1200 m2 underside of 01 deck
Installation date: Aug2010

Project: Thermally sprayed anode for Dyke 1 Dolphins 2 & 3, Dyke 2 Dolphin 6
Client: Newcastle Port Corporation (NPC)
Scope: Zinc Anode application to 3 concrete Dolphins including 3 test & monitoring panels. Total area 330 m2
Installation date: June & July 2011

Project: Thermal Spray of all facilities within the terminal
Client: PKCT (Port Kembla Coal Terminal)
Installation date: Commenced 2010 - Ongoing to date

Project: Thermal aluminium spray of ducts & vessels in the Acid Plant
Client: VALE GORO
Owner:GORO Nickel
Scope: New Caledonia
Installation date: 2010,11,12 &14 

Project: Thermal spray of irrigation radial gates
Client: Coleambally Irr
Owner:Coleambally Irr
Scope: structures and bores
Installation date: since 2001 - Ongoing